Monday, 24 February 2020

Mid Sem Syllabus for CEE (8TH SEM) 2180901

Government Engineering College, Bharuch
Electrical Engineering Department
Mid Sem Syllabus  for CEE  (8TH SEM) 2019



Chapter no - 1
   Safety Management:
 Objectives, Safety Management during Operation and Maintenance, Clearance and Creepages, Electric Shock, need of Earthing, different methods of Earthing, factors affecting the Earth Resistance, methods of measuring the Earth Resistance, Equipment Earthing and System Grounding, Earthing Procedure - Building installation, Domestic appliances, Industrial premises, Earthing of substation, generating station and overhead line.


Chapter no - 2

Installation of Electrical Equipment:
Inspection of Electrical Equipment at site, Storage Electrical Equipment at site, Foundation of Electrical Equipment at site, Alignment of Electrical Machines, Tools/Instruments necessary for installation, Technical report, Inspection, storage and handling of transformer, switchgear and motors.





Chapter no - 3

Testing of Transformer, Plant and Equipment:
General Requirements for Type, Routine and Special Tests, Measurement of winding resistance; Measurement of voltage ratio and check of voltage vector relationship; Measurement of impedance voltage/short-circuit impedance and load loss; Measurement of no-load loss and current; Measurement of insulation
resistance; Dielectric tests; Temperature-rise, insulation and HV test, dielectric absorption, switching impulse test. testing of Current Transformer and Voltage Transformer, power transformer, distribution transformer, CVT and special transformer with reference to Indian Standard (IS). Drying out procedure for transformer. PI index, Commissioning steps for transformer, Troubleshooting & Maintenance of transformer.
[Ref: IS 2026:Part_1-10-Power Transformers: Methods of Test; IS 13956:1994-Testing Transformers]



Chapter no - 4



Installation and commsissioning of Rotating Electrical Machines:
Degree of protection, cooling system, degree of cooling with IP- IC code (brief discussion), enclosures, rating of industrial rotating electric machine, installation, commissioning and protection of induction motor and rotating electric machine, drying out of electric rotating machine, insulation resistance measurement, site testing and checking, care, services and maintenance of motors, commissioning of synchronous generator, protection and automation of synchronous generator, synchronous motor, D.C. generator and motor with reference to Indian Standard (IS).
[Ref: IS 4029:2010-Guide for Testing Three Phase Induction Motors; IS 7132:1973-Guide for Testing Synchronous Machines; IS 9320:1979-Guide for Testing of Direct Current (dc) Machines]




No comments:

Post a Comment